Guide

How to Measure for a Concrete Slab

Measure length, width and thickness for a concrete slab and turn it into cubic yards and bags, with two worked examples and common mistakes.

Ordering a slab right starts with three measurements and one decision. Get those, and the concrete volume falls out of a simple calculation. This guide walks through each step, gives two worked examples, and lists the mistakes that lead to a short or wasted order.

Step 1: measure the footprint

Measure the length and width of the slab in feet. For an irregular shape, split it into rectangles and add the areas, the same way you would for any surface. Measure to the inside of your forms, since that is the actual space the concrete fills, and check the diagonals to confirm the form is square.

Step 2: choose the thickness

Thickness depends on the load the slab will carry. Four inches suits patios, walkways and shed floors. Driveways for cars are 4 to 5 inches, and garage floors or anything taking heavy vehicles are 5 to 6 inches. A thickened edge or a non level subgrade adds volume, so measure the realistic deepest case rather than the design thickness alone.

Step 3: work out the volume

Multiply length by width by thickness in feet, then divide by 27 for cubic yards. Convert the thickness from inches to feet by dividing by 12.

cubic yards = length × width × (thickness ÷ 12) ÷ 27

Step 4: add waste and convert to bags

Add about 7 percent for spillage and an uneven base, then round up. If you are using bags, an 80 pound bag yields about 0.60 cubic feet, a 60 pound bag 0.45, and a 40 pound bag 0.30.

Bag sizeYieldBags per cubic yard
80 lb0.60 cu ftabout 45
60 lb0.45 cu ftabout 60
40 lb0.30 cu ftabout 90

Worked example one: a patio

A 10 by 10 foot patio at 4 inches: 10 times 10 is 100 square feet, times 0.333 feet is 33.3 cubic feet, divided by 27 is about 1.24 cubic yards before waste. That is roughly 56 of the 80 pound bags. With a 7 percent allowance, round up to about 60 bags, or order one and a third cubic yards of ready mix.

Worked example two: a garage floor

A 20 by 22 foot garage floor at 5 inches: 440 square feet times 0.417 feet is about 183 cubic feet, divided by 27 is about 6.8 cubic yards. With waste, order about 7.3 cubic yards. At this size you would never bag it, since that is over 300 bags. This is firmly ready mix territory.

When to switch to ready mix

Mixing 56 bags by hand is a long, hard day and risks cold joints between batches. Once you approach a cubic yard, ready mix delivered by the truck is usually cheaper and far easier, and it gives one continuous pour with consistent strength.

Common mistakes

  • Measuring the thickness as the design figure when the subgrade dips, which leaves you short.
  • Forgetting a thickened edge, common around the perimeter of a slab.
  • Ordering with no waste, then running out part way through the pour.
  • Bagging a job that is really a ready mix job, turning one delivery into a punishing day of mixing.
Get your exact amount. Concrete Calculator →

Common questions

How much concrete for a 10 by 10 slab at 4 inches?

About 1.24 cubic yards before waste, roughly 56 of the 80 pound bags. Add 7 percent and round up.

How thick should a slab be?

Four inches for patios and walkways, 4 to 5 inches for car driveways, and 5 to 6 inches for garage floors and heavy loads.

Do I measure inside or outside the forms?

Measure to the inside faces of the forms, since that is the space the concrete actually fills.

Should I order bags or ready mix?

Bags suit jobs under a cubic yard. Past that, ready mix is usually cheaper and avoids cold joints from separately mixed batches.

How much concrete for a garage floor?

A 20 by 22 floor at 5 inches is about 6.8 cubic yards before waste, firmly ready mix territory.
Knowledge Base

Estimating Guides & Reference

Plain-language guides on measuring, coverage and how much extra to buy, written for DIYers and trades.

Measuring & Estimating
Concrete & Aggregate
Soil & Lawn
Interior & Finishing